Development Plan Status & Preparation

Brynmawt Town Square

The Council has resolved to cease work on the Unitary Development Plan and commence work on the Local Development Plan.

Development Plan In Force

Blaenau Gwent Unitary Development Plan

Adopted July 6 2006

Local Development Plan Preparation to date

Blaenau Gwent Local Development Plan

Formal preparation commenced 1 November 2006

Delivery Agreement

Consultation period 15 December 2006 - 26 January 2007

Delivery Agreement submitted to Welsh Assembly Government for agreement: 3 April 2007

Delivery Agreement agreed by Welsh Assembly Government: 3 May 2007

Revised Delivery Agreement submitted to Welsh Assembly Government: December 2010

Revised Delivery Agreement agreed by the Welsh Assembly Government: January 2011

Candidate Sites

Call for Candidate Sites 25 April to 29 June 2007. 

Issues Paper Consultation period 6 July 2007 - 8 August 2007 
Sustainability Appraisal / Strategic Environmental Assessment Consultation on the draft Scoping Report: 9th November 2007 - 14th December 2007
Pre-deposit Public Consultation Consultation on the draft Preferred Strategy and the Initial Consultation Report: 7 November 2008 - 19 December 2008
Statutory Deposit of Proposals Deposit Plan Consultation: 5 May 2011 - 16 June 2011
Alternative Sites Consultation Alternative Sites Consultation: 21 July 2011 - 1 September  







 

 

 

 

Contact Information

For further information please contact

Planning Policy
Business Resource Centre
Tafarnaubach Industrial Estate
Tredegar
NP22 3AA

Telephone: (01495) 354740/ 355538/ 355544

Email : planningpolicy@blaenau-gwent.gov.uk